Fairfield Inn

Fairfield 002 580

This new 114 room mid-rise hotel follows the prototype design created for Marriott’s business traveler.  Bristol has adapted the Marriott design to an economic yet structurally superior pre-cast system; providing faster delivery cycles and quicker returns.

Project Specs
Building Type and Size: 6-Story Hotel, 65,000 sq.ft.
Location: Lexington, KY
Owner/Client: Mahair Enterprise, LLC
Construction Cost: $7,566,000
Delivery Method: Design/Build
Schedule: Fast Track, 12 Months; Design and Construction
Completion: 2009

 

Innovative construction techniques casting walls and beams, both on and off site allow Bristol to minimize transportation cost, and get the project under roof before winter conditions arrive. Additional building elements include thin brick veneer for the ground floor panels, cast in place concrete columns and pre-cast interior shear walls. The project was under roof in less than 6 months and completed in 11 months.

Fairfield 003 580

Fairfield 004 580